Trusted Boot
|
|
============
|
|
|
|
Terminology
|
|
-----------
|
|
|
|
* TBM: Trusted Boot Module (the entire system) or Trusted Boot Manager (the ARM Cortex M0 or AVR
|
|
microcontroller).
|
|
* ROTS: read-only trusted state.
|
|
|
|
Prerequisites
|
|
-------------
|
|
|
|
* SPI NOR Flash to store a minimalistic read-only Linux image without networking support.
|
|
* ARM Cortex M0 or AVR microcontroller.
|
|
* A programmable timer to set deadlines and to trigger an interrupt when these expire.
|
|
* Possibly SPI NOR Flash for the Trusted Boot Module to store information.
|
|
* Key storage and management.
|
|
* The option of image rollback?
|
|
|
|
Trust Model
|
|
-----------
|
|
|
|
There are different trust models that can be used depending on the use case.
|
|
These mostly depend on whether the concept of certificate authorities (CAs) is required or not.
|
|
Furthermore, the key storage also plays an important role in deciding which of the trust models to
|
|
use.
|
|
|
|
#. "Home router"
|
|
CA: none
|
|
|
|
* replace = reflash RO flash
|
|
|
|
#. "Routers in company, sysadmin"
|
|
CA: none
|
|
|
|
* replace = reflash or signed statement
|
|
|
|
#. "Routers with CA"
|
|
CA: one.
|
|
|
|
* replace CA = reflash ROTS
|
|
* replace key = by signed CA statement
|
|
|
|
#. "Routers with multiple CAs"
|
|
CA: multiple.
|
|
|
|
* replace CA = threshold
|
|
* replace key = by signed CA statement.
|
|
|
|
#. "Routers with multiple CAs and initial CA in ROTS"
|
|
CA: multiple.
|
|
|
|
* revoking keys, which is not the same as removing keys.
|
|
|
|
#. CA: multiple.
|
|
|
|
* replace CAs = reflash ROTS.
|
|
* replace key = by signed CA statement
|
|
|
|
Key Storage
|
|
-----------
|
|
|
|
* RO Flash
|
|
* TBM
|
|
* Box storage (e.g. HDD)
|
|
* Signed statements by embeddeding keys in images.
|
|
|
|
Forced reboot
|
|
-------------
|
|
|
|
Because the image is only trusted up to the extent that the user trusts the parties that have
|
|
signed the image, the image may contain vulnerabilities that the user will only be aware of at a
|
|
later point.
|
|
As these vulnerabilities can be used to compromise the system in such a way that it will prevent
|
|
from rebooting the system, it is important that the TBM can reboot the system.
|
|
The straightforward method of performing such a forced reboot would be to set a deadline that can
|
|
be postponed by the user up to *n* times, whereupon the TBM will simply force a reboot after these
|
|
attempts or when the user decides to reboot gracefully.
|
|
|
|
Upgrading
|
|
---------
|
|
|
|
One possible attack vector is that when the image that is running has been compromised in such a
|
|
way that it prevents the system from running the update process, even after a reboot, then this
|
|
will force the system to always boot the version installed.
|
|
To mitigate this we could split up the image into two stages.
|
|
The read-only trusted stage will then first boot up a minimalistic environment within the image to
|
|
check for updates and to perform them, whereupon the full image will be booted.
|
|
Because it is impossible to update the read-only trusted stage as it is stored on a read-only
|
|
medium, we want to prevent the read-only stage from being able to perform updates, as it will
|
|
require a network stack as well as TLS support.
|
|
Both the network stack and TLS support are hard to implement correctly, thus they are both open to
|
|
many vulnerabilities that cannot be mitigated as the read-only trusted stage cannot be updated.
|
|
This is why the read-only trusted stage cannot be responsible for checking for updates and
|
|
performing updates.
|
|
Therefore, in combination with the concept of a forced reboot from the TBM, the system would always
|
|
be able to check for updates periodically.
|
|
|
|
To keep track of the images, a table can be used to mark whether the update stage and the image
|
|
itself are known to work.
|
|
Based on that table the Trusted Boot Manager can then determine which image to rollback to in case
|
|
the updated image does not work.
|
|
Furthermore, one important decision is whether to only use images that are known to fully work or
|
|
to specifically select working stages separately.
|
|
Another important open question is how far back the system is allowed to rollback.
|
|
|
|
Initial Keys and Configuration
|
|
------------------------------
|
|
|
|
The initial key(s) or certificates and the configuration for the TBM could be presented on a SD
|
|
card that is inserted before the system is booted for the very first time.
|
|
Alternatively, we could decide to have the user embed the keys within the ROTS image before
|
|
flashing it to the RO Flash.
|
|
Another option would be to offer the user the option of performing key management by means of
|
|
serial communication with the Trusted Boot Manager.
|
|
|
|
Verification of images
|
|
----------------------
|
|
|
|
As the user added the keys from the signing parties to trust, the system should only allow images
|
|
that have been signed with these keys.
|
|
This verification can take place in the read-only trusted stage before booting the image to ensure
|
|
that it has not been comprimised.
|
|
Furthermore, as there is a notion of reproducible builds, there is the option of verifying the
|
|
packages within the image.
|
|
However, as the read-only trusted state should be kept simple to avoid any possible vulnerabilities
|
|
or compromises, it is better to delegate the responsibility of verifying these packages to the
|
|
parties that sign the image.
|
|
Similarly, while the idea of sending deltas between different versions of images does sound
|
|
beneficial in the sense that the amount of data that has to be downloaded is kept to a minimum,
|
|
this would also further complicate the read-only trusted stage to the extent that it could increase
|
|
the likelihood of possible vulnerabilities.
|
|
|
|
Boot procedure
|
|
--------------
|
|
|
|
#. The image from SPI flash is read and booted.
|
|
#. The read-only trusted stage asks the Trusted Boot Manager what to boot and/or asks whether it
|
|
is allowed to boot a certain image.
|
|
By default the read-only trusted stage should boot a semi-trusted update stage.
|
|
#. The read-only trusted stage boots the semi-trusted update stage using ``kexec``.
|
|
#. The semi-trusted update stage checks for updates and downloads a new image if present.
|
|
#. Once downloaded the semi-trusted update stage finishes by telling the Trusted Boot Manager that
|
|
a new image has been downloaded or that no updates were available.
|
|
#. The Trusted Boot Manager reboots the system.
|
|
#. The image from SPI flash is read and booted.
|
|
#. The read-only trusted stage asks the Trusted Boot Manager what to boot and/or asks whether it
|
|
is allowed to boot a certain image.
|
|
After a reboot from the update process, the Trusted Boot Manager will tell the read-only
|
|
trusted stage to boot the latest image.
|
|
#. The read-only trusted stage uses ``kexec`` to boot the latest image.
|
|
|
|
Image self-test and rollback
|
|
----------------------------
|
|
|
|
The image could be extended with a self-test, where the untrusted stage tells the Trusted Boot
|
|
Manager that it managed boot successfully.
|
|
In case the image fails to boot, the Trusted Boot Manager should set a deadline to expire before
|
|
the image is booted.
|
|
When this deadline expires, the Trusted Boot Manager can then assume that the image does not work
|
|
and should not be used in the future, allowing rollback to the last-known working image.
|
|
Furthermore, by solely working with the concept of a last-known working image and an updated image
|
|
the possibility of a downgrade is severely limited and no advanced implementation of an image
|
|
rollback system would be required.
|
|
|
|
Trusted Boot Manager protocol
|
|
-----------------------------
|
|
|
|
To have the board communicate with the TBM, we have to devise a protocol.
|
|
This communication is likely to place over serial communication through the UART ports.
|
|
Furthermore, the board can only send requests to the TBM to which the TBM responds, i.e. the TBM
|
|
should never be able to initiate communication.
|
|
In the read-only trusted stage the Trusted Boot Manager fully trusts the system and as such the
|
|
read-only trusted stage can operate using the full scope of the protocol.
|
|
At some point the TBM will be informed by the read-only trusted stage that it will boot into
|
|
untrusted state, which is an indication for the TBM to configure the deadline timer and that the
|
|
scope of the protocol should be limited as the untrusted stage is only allowed to inform the TBM
|
|
that it booted successfully.
|
|
The read-only trusted stage should be able to ask which images are preferred for booting and if
|
|
booting a certain image is allowed.
|
|
Furthermore, it would probably be interesting if a list of images that can be booted can be queried
|
|
from the TBM.
|
|
In the case that we decide to support initial communication from the read-only trusted stage,
|
|
either by flashing the RO Flash or by inserting a removable medium such a SD card, it might be
|
|
interesting to support this option of configuration in the protocol.
|
|
|
|
Proposal(s)
|
|
-----------
|
|
|
|
To reduce the amount of possible vulnerabilities, the codebase and complexity of the TBM should be
|
|
kept as minimalistic as possible.
|
|
From that point of view, it would be best that the read-only trusted stage only consists of the
|
|
tools necessary to verify signed images, to communicate with the TBM and to ``kexec`` those images.
|
|
Furthermore, since the read-only trusted stage cannot be modified once it has been written to the
|
|
RO Flash, it cannot be easily patched.
|
|
As such, it makes a lot of sense to not include a network and TLS stack, as it is very likely that
|
|
they contain many vulnerabilities that have yet to be found.
|
|
Separating the update stage from the actual image itself, allows the system to forcefully perform
|
|
updates, which would essentially prevent any attacker from extending the time window they have any
|
|
further.
|
|
However, similar to the read-only trusted stage, the update stage should only come with the tools
|
|
necessary to check for updates and to perform an update: a network stack, a TLS stack and tools to
|
|
communicate with the TBM.
|
|
Finally, from the point of view of maintaining minimalism, only allowing rollback to the last-known
|
|
working image of which both the update stage and the image itself is probably one of the most
|
|
elegant choices, as it easily prevents downgrade attacks and as it is easier to implement.
|
|
|